Ha Noi – Hai Phong Expressway Project

Execution progress of Packages EX7 and EX10, Hanoi – Hai Phong Expressway Project

These two packages are funded by Korea in form of ODA with total amount of USD 200 million and executed by the Korean Contractors, i.e. GS E& C and Namkwang E&C respectively.

 

These two Contractors have completed the procedures as required; completed their mobilisation of manpower and construction equipment; established management offices and laboratories.


Construction site of Package EX-7, Hanoi - Hai Phong Expressway Project.

Package EX-7 is executed by GS E&C and was commenced on 3 February 2009. To date, USD25.4 million has been disbursed to the Contractor. However, the Project progress is delayed as against the schedule due to some obstructions in land acquisition and changes of the detailed design (profile, soft soil ground treatment measures).


Construction site of Package EX-10, Hanoi - Hai Phong Expressway Project.

Package EX10 is executed by Namkwang E&C and was commenced on 2 November 2009. To date, USD15.4 million out of USD100 million has been disbursed to the Contractor. This Package is located at the ending section of the Expressway with complicated terrain and goes through several marshes. Therefore, the soft soil treatment faces a lot of difficulties. In addition, there exist several obstructions in land acquisition thereto.

Thanh Tùng - VDB